Expansion Joints – Part 2

In an earlier blog post I mentioned my preoccupation with expansion joints. These thin vertical  joints in the mosaic are prepared by using 1/16″ pin striping tape and thin rope to designate clean lines that are filled with a flexible caulk (instead of grout) to allow for small amounts of movement within the concrete. 

Soon after grouting , the rope used to protect each vertical expansion joint line is carefully removed and the gap is filled with the flexible caulk. We have installed 9 of these expansion joints that are now filled with caulk and nearly impossible to see in the finished mosaic mural.

There are four caulked expansion joints in the part of the mural where a crack in the concrete was repaired by Joe McCarty (www.joetile.com). Can you see them? (I can’t.)

 

Looks Like Magic…

José Orantes and I have continued the installation process of the mosaic mural for seven full work days since my last post. Most days we’ve met at playground at 7AM and spend about 45 minutes setting up our tarp canopies, organizing our tools and materials and making a plan for our day. These past few days, José has been grouting the parts that are ready and I’ve been doing the detail work. For folks that come by the wall once a week, our (slow,  persistent) progress looks like magic. That’s just an illusion 🙂

The park is quiet early in the morning. This installation is feet away from the storage room that houses electricity and access to a water hose. It’s also right near the restrooms. The tarp tent feels like a home and provides shade. I’m sure I’ll miss the mornings working here in the playground. We’ve also had the opportunity to chat with folks that walk through the playground during these quiet times. We’re touched by their compliments of the mural-in-progress. It’s so nice seeing Janice Engvall who I knew from when my kids were a Lakeridge, walk by each morning with her husband. This week she said “I walk by every day and now instead of seeing the concrete, I’m watching the wall evolve into beautiful artwork!” 

Here are some photos that illustrate our progress:

Thanks also to some of our friends who stopped by to volunteer this week. Here are a few captured at work. Thanks also to Bonni, Sari and Kathy!

In my next post, I’ll share some details about the detail work. Thanks for checking in.

Installing Tiled Mosaic Mural: Days 3-5

IMG_3214

Mixing thinset

Wednesday through Friday have been sunny, dry, and warm. We’re grateful for the tarp canopy that provides some shade while we continue to install the tiled mosaic mural at Luther Burbank Park.

The dry warm and sometimes breezy weather causes the thinset to dry faster. José makes small batches so that our adhesive doesn’t dry out before we are able to install the panels of mosaics. 

 


Making progress on the mosaic mural

Day 3: By the end of the third day of installing, we’re able to see Jose’s painting coming together in the tiled mural! We start at the bottom (E) and move up in a stepping pattern, taking care to maintain the 1/16″ spacing between tiles and using a small level to assure that the vertical and horizontal lines remain plumb.


Installing Expansion Joints 

In addition to painting a coat of RedGard® on the wall, we’re installing expansion joints to prevent damage from cracks in the concrete.The rope is removed after grouting. The space is then filled with a flexible caulking instead of grout to allow for expansion due to small cracks in the concrete.


The mural continues to grow…

We continue to install about 35 -40 square feet each day during days 4 and 5 (8/11 and 8/12). Whew! Thank you to Carole for working with us on Thursday and for talking us to Master Wholesalers to buy more thinset in “Beastie” and to Libby for helping out on Friday. 

We’re taking the weekend off but will be back
at 7AM on Monday!
♦♦♦

Installing Tiled Mosaic Mural: Days 1 & 2

José Orantes and I are back at the Luther Burbank Park playground installing mosaics on the 5′ high x 38′ long concrete wall. Here’s the progress we’ve made on Monday and today working from 7 AM – 3PM.


~ Day 1 ~

1. Build Tarp Canopy for our workspace 

Materials:
~ 16’ x 20’ tarp (cut into two to 8’ x 20’ lengths)
~ Four bar clamps to attach to the top of the concrete wall
~ Eight 1” x 2” wood strips to create structure.
~ Canvas drop cloth (9’ x 12’ cut to 4.5’ x 9’) to cover ground

2. Paint the wall with Red Guard to reduce cracking

We applied a coat of RedGard® to provide a flexible barrier between the concrete and the mosaic installation as a precaution to reduce the effects of cracks in the concrete. We’ll also be install several expansion joints in the affected area and every eight feet as recommended by tile experts.

Materials:
~ 3.5 gallons of RedGard®
~ Rollers and extension rod
~ Paint pan and disposible liner
~ Tape to protect surfaces


Day 2

Another busy work day that included lots of measuring and remeasuring, creating a gridded prep table to set out our tiled mosaic art in position before installation, installing stainless steel schluter edging and beginning to install the mural.

1. Create Tile Prep Table

Our prep/set-up table is carefully measured, gridded and labeled to hold our mosaic panels in position before installing them onto the concrete wall. Numbers along the top are marked on blue tape so that we can update the columns as we move across the wall in our installation process. The letters A, B, C, D, E represent placement from top to bottom.

Materials:
~ Three work horses to hold plywood table
~ plywood cut and assembled to fit 5′ x 7′ of mosaics
~ Roller and paint pan
~ Primer
~ Ruler, pencils and Sharpie markers

2. Installing Schluter and mosaics!

We’re feeling brave! 

We’ll be back again tomorrow at 7AM.

Preparing to install the tiled mosaic

The to-scale painting that José Orantes created over 9 months ago has been enlarged and reproduced onto mosaic mesh using 10mm (1/4″) glass tiles instead of paint. The 12.5″ squares of glass tile adhered to mosaic mesh was sent to me via UPS! It was so exciting and mind boggling to receive ten boxes, each weighing approximately 30 pounds, knowing that when installed on the 5′ high by 38′ long concrete wall in Luther Burbank Park (above the playground), the mural will come to life in a tiled, pixelated impressionistic work of art.

See how the “A3” tiled square matches up to its designated square on the “road map”?
José and I are thrilled with the range of colors used to recreate the painting.
Some are even iridescent! 


~ Building in Longevity ~

Expansion Joints:
expansion joint
We’ll install expansion joints every eight feet to protect the mural from movement that can occur within the concrete over time. This image (http://www.poolspanews.com/how-to/design-construction/special-report-glass-tile_o) illustrates how expansion joints between the rows of tile is created by placing a flexible sealant where grout normally would go. The flexible filler should absorb stress and allow space for the tile to expand and shift without cracking.

We will paint a coat of Custom Building Products’ Red Guard on the concrete substrate prior to installing the mesh-backed tile as an additional precaution to prevent cracking.

 


Creating a tarp canopy:

Before we begin our work to install the mosaic mural, José has conceived a design for a tent that will shield our installation, materials and us (!) from the sun. We’ll attach a tarp to the top of the concrete wall using four bar clamps. 1″ x 2″ wooden strips will be built into the tarp to provide structure. While we work, the tent will provide shade.

When we are done working for the day, the tarps will be released so that our work-in-progress will be protected.

Materials:
– 16’ x 20’ tarp (we will cut it to 8’ x 20’
–  4 bar clamps to attach to the top of the concrete wall
–  1” x 2” wood strips to create structure.

I’m continuing to develop a checklist detailing the process and the supplies we need to bring to the site so we don’t forget anything. Here were go!